LansingTop story
Lansing's Town Board votes today on a data center ban after a packed hearing
The Lansing data center fight runs back to August 2025
- Aug. 2025Lake Hawkeye LLC, a TeraWulf subsidiary, signs an 80-year lease for the plant site.
- JulyGov. Kathy Hochul signs a one-year moratorium on hyperscale data center environmental permitting.
- Sept. 29The ban is proposed at the end of a special Town Board meeting.
- Nov. 3TeraWulf files an Article 78 petition over the town supervisor's FOIL responses.
- Nov. 17A public hearing on the ban fills the Lansing Middle School auditorium.
- Nov. 18The Town Board is set to decide on the ban.
Sources: The Cornell Daily Sun, WSTM
If you live in Lansing, today's the day. The Town Board is set to decide whether to ban data centers, a day after a packed hearing. WSTM reports the proposal also covers cryptocurrency mining facilities and would apply townwide, not to one project.
At Lansing Middle School Tuesday night, 48 people signed up to speak, with two minutes each. Many wore red to back the ban. TeraWulf representatives opposing it were met with boos.
- Cost: town FOIL requests topped $200,000, October 2025 to mid-June
- State moratorium: one year without environmental permits for hyperscale centers
The Ithaca Voice reports the former plant site has a roughly 40-acre coal ash pile. A 1994 state report scored it 37.63 on the Hazardous Ranking Score. The minimum for the EPA's Superfund list is 28.5. A DEC spokesperson said post-closure monitoring data for the closed landfill “indicates that no more remedial action is necessary.”
The site's 1994 score topped the Superfund minimum
Source: The Ithaca Voice
View as table
| Value | |
|---|---|
| Site's 1994 score | 37.63 |
| Superfund list minimum | 28.5 |